this is a break down of one working day last week(tues 25th march)
sad as it sounds i actually timed myself reeling in :

i did it for the whole day at every job,timing is for the time spent turning the reel
time does not include walking the tap back to the van and laying the hose out ( i do this anyway and so would anyone using an electric reel,it is the best method imo of making reeling in easier and no one wants their tap/shrader bouncing along the ground)
all times are rounded UP to nearest 5 seconds
on most jobs only about 75mtrs or so were off the reel
job 1; 25 secs
job 2; 25 secs
job 3; 35 secs
job 4; 55 secs
job 5; 30 secs
job 6; 20 secs
job 7; 20 secs
jobs 8 + 9 ; 1 min 10 secs
job 10 ; 25 secs
job 11 ; 35 secs
job 12 ; 15 secs
thats it,nothing really scientific just timed off the sweep hand on my watch
not looking to prove anything it was just something to help pass the day