bobplum

  • Posts: 5602
for those that use aworka...settings
« on: October 13, 2013, 10:42:21 am »
i am trying to work out the best settings to use for monthly customers.

I am finding that jobs are bunching together on certain days and a lot of it has to do with the settings,

In the Planner section:
On "allowed days" i have opted for MON - FRIDAY and in the planner section  were it says "re plan from" i have opted for "last job date".

does anyone do it differently, i have asked Chris and he as provided some info but thought i would ask those that use it out in the field


cheers bob

Mike #1

  • Posts: 4668
Re: for those that use aworka...settings
« Reply #1 on: October 13, 2013, 11:55:35 am »
I re plan from job date and on allowed days i have Mon-Sat . Mike

bobplum

  • Posts: 5602
Re: for those that use aworka...settings
« Reply #2 on: October 13, 2013, 12:02:20 pm »
I re plan from job date and on allowed days i have Mon-Sat . Mike

Do you get jobs overlapping

dave0123

  • Posts: 3553
Re: for those that use aworka...settings
« Reply #3 on: October 13, 2013, 01:03:50 pm »
are you selecting monthly or 4 weekly?
Dave.

Ian Lancaster

  • Posts: 2811
Re: for those that use aworka...settings
« Reply #4 on: October 13, 2013, 05:38:32 pm »
We allow all days.  If you have to work a weekend for any reason it stops the problems of overlapping and if you don't it doesn't make any difference.

That's provided you plan multiples of a week, not dates in a month.

bobplum

  • Posts: 5602
Re: for those that use aworka...settings
« Reply #5 on: October 13, 2013, 07:09:01 pm »
are you selecting monthly or 4 weekly?

monthly

bobplum

  • Posts: 5602
Re: for those that use aworka...settings
« Reply #6 on: October 13, 2013, 07:09:41 pm »
We allow all days.  If you have to work a weekend for any reason it stops the problems of overlapping and if you don't it doesn't make any difference.

That's provided you plan multiples of a week, not dates in a month.

so would that be a 4 weekly system you work to

Mike #1

  • Posts: 4668
Re: for those that use aworka...settings
« Reply #7 on: October 14, 2013, 08:01:40 am »
I never get any overlap i schedule my work 4 weekly on the odd rare occassuin i have had it were far to much work has ended up in one day .

But i just shift as needed it all works out never had any issues as such in 19 months . Mike

bobplum

  • Posts: 5602
Re: for those that use aworka...settings
« Reply #8 on: October 14, 2013, 08:25:51 am »
I never get any overlap i schedule my work 4 weekly on the odd rare occassuin i have had it were far to much work has ended up in one day .

But i just shift as needed it all works out never had any issues as such in 19 months . Mike

chris has advised doing 4 weekly and treating like a monthly schedule so will be returning to this way