I am assuming block-paving.
For 3300 sqm you'll need a small team and several machines if you've got to get the job done in a sensible amount of time. I reckon 180 hours divided by three operators should make this job possible in a long week.
If doing on your own (wash, weedkiller, sand) with a decent machine (3000 psi, 15 LPM min) then you can probably add to the 180 due to operator fatigue.
Really poor drainage could add to the time.
If the surface is blocks then I'd estimate that you'll have to shovel and dispose of anywhere between 300 + 500 buckets of mixed crap and undrained water.
Check policy on disposal with the customer.